a) Scope: The project adds 5MW on each of the two 26.35MW units through modernisation and upgrade of 2 generation units.
b) Project Impact: The project will improve plant reliability and increase capacity by 10 MW.
c) Progress: The progress of the project is as detailed in the Table below:
| Progress to date |
|