+265 1 836 000

a)a) Scope: The project involves coming with specifications, designing, manufacturing, installation, testing and commissioning of generation plant.

b) Project Impact: The project will improve machine reliability and add 12 MW capacity to generation system.

c) Progress: The progress of the project is at 40% and is as detailed in the Table below:

Progress to date
  • Most parts have been manufactured, factory inspections on key parts was being done.
  • Civil contractor was mobilizing on site and some civil preparatory works were underway.
  • Delivery of some items was under way.
  • Dismantling of old plant near completion.
  • Cofferdam to isolate the station complete.