+265 1 836 000

a) Scope: The project involves capital dredging at Tedzani Intake reservoir and diverting a stream thatdeposits silt into the reservoir downstream of the barrage.

b) Impact: The project will: reclaim headpond live storage capacity at Tedzani and reclaim the lost effective installed capacity by 36MW reduce the inflow of silt Enhance the viability of Tedzani IV Project

c) Progress: The progress of the project is as detailed in the Table below:

Progress to date
  • Contract was awarded