a) Scope: The project entails procurement and installation of 20MW of Peaking Diesel Generation Sets for Mapanga.

b) Impact: Project will provide additional capacity for peaking, standby and for system voltage improvement.

c) Progress: The progress of the project is as detailed in the Table below:

Progress to date
  • Contract for additional 20MW for Mapanga was signed on 22nd April 2017.
  • Project designs and drawings were approved Contractor commenced site clearing.